51ÂÒÂ×»»ÆÞ

Port St. Joe-Callaway 230kV Transmission Line Upgrade Project

Type:Ìý°Õ°ù²¹²Ô²õ³¾¾±²õ²õ¾±´Ç²Ô
Scope: Performed the removal and rebuild of 34 miles of 230kV transmission line in the aftermath of Hurricane Michael.
Location: Port St. Joe, Florida
Client: Duke Energy

is one of the largest electric power holding companies in the United States, providing electricity to 7.7 million retail customers in six states. In December 2018, Duke Energy contracted Irby to perform the removal and reconstruction of 34 miles of 230kV transmission line from Port St. Joe to Callaway in the aftermath of Hurricane Michael.

The work scope was completed ahead of schedule in March 2019 with no injuries or environmental incidents with the assistance of several key subcontractors including , , , , ROW Masters, , and .

Start Date: December 2018
Completion Date: March 2019

 

If you would like to request information on this project or submit a request for bid,Ìýclick here.Ìý